Bakers Forge Memorial Cemetery, Removal Order, Contract, and Card (W-Wh)

 File — Box: 4, Folder: 1
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Bakers Forge Memorial Cemetery, Removal Order, Contract and Card (Wi)

 File — Box: 4, Folder: 2
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Bakers Forge Memorial Cemetery, Removal Order, Contract and Card (Wo-Y)

 File — Box: 4, Folder: 3
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Davis Chapel Cemetery, Removal Order, Contract, and Card

 File — Box: 4, Folder: 4
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Will Springs Cemetery, Removal Order, Contract, and Card

 File — Box: 4, Folder: 5
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Stokes Cemetery, Removal Order, Contract and Card

 File — Box: 4, Folder: 6
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Housley Cemetery, Removal Order, Contract and Card

 File — Box: 4, Folder: 7
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Alvis McCarty Cemetery Removal Order, Contract and Card

 File — Box: 4, Folder: 8
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

W. L. Beeler Cemetery Removal Order, Contract and Card

 File — Box: 4, Folder: 9
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Robert Lett Cemetery Removal Order, Contract and Card

 File — Box: 4, Folder: 10
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Ridenour Cemetery Removal Order, Contract and Card

 File — Box: 4, Folder: 11
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Milan Baptist Church Cemetery Removal Order, Contract and Card

 File — Box: 4, Folder: 12
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Oak Grove Cemetery Removal Order, Contract and Card

 File — Box: 4, Folder: 13
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

R. B. Snodderly Cemetery Removal Order, Contract and Card

 File — Box: 4, Folder: 14
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Leabow Cemetery Removal Order, Contract and Card

 File — Box: 4, Folder: 15
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Riddle Cemetery Removal Order, Contract and Card

 File — Box: 4, Folder: 16
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Taylor Cemetery Removal Order, Contract and Card

 File — Box: 4, Folder: 17
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Stanley Cemetery Removal Order, Contract and Card

 File — Box: 4, Folder: 18
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Indian Creek Memorial Cemetery Removal Order, Contract and Card (A-B)

 File — Box: 4, Folder: 19
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936

Indian Creek Memorial Cemetery Removal Order, Contract and Card (C-D)

 File — Box: 4, Folder: 20
Scope and Contents Note From the Collection:

This collection houses the Tennessee Valley Authority's records of graves removed before the construction of the Norris Dam in East Tennessee, the first major project of the TVA. The collection houses cemetery removal orders, contracts, and cards for over seventy cemeteries.

Dates: circa 1933-1936